File #: Res 2020-69    Version: 1 Name: Resolution Authorizing Award of Contract for Installation of Traffic Signals on East 120th Avenue at E-470 to W.L. Contractors, Inc.
Type: Resolution Status: Passed
File created: 8/25/2020 In control: City Council
On agenda: 9/21/2020 Final action: 9/21/2020
Title: RESOLUTION AUTHORIZING AWARD OF CONTRACT FOR INSTALLATION OF TRAFFIC SIGNALS ON EAST 120TH AVENUE AT E-470 TO W.L. CONTRACTORS, INC.
Attachments: 1. Resolution, 2. Draft Contract, 3. IGA, 4. Council Memo

Title

RESOLUTION AUTHORIZING AWARD OF CONTRACT FOR INSTALLATION OF TRAFFIC SIGNALS ON EAST 120TH AVENUE AT E-470 TO W.L. CONTRACTORS, INC.

 

Body

Summary and Background Information

The E-470 Authority identified the need for a traffic signal at the interchange of East 120th Avenue and E-470. Since the City was in the process of bidding out traffic signals along 104th Avenue, E-470 approached the City with the idea of collaborating with us to help get the traffic signal constructed at the interchange of 120th Avenue and E-470. An Intergovernmental Agreement was completed in August of 2019 between the City and E-470, which establishes the work responsibilities and funding. The E-470 Authority has agreed to provide the City funding for design, construction, and construction management in an amount up to $750,000.

 

The poles and mast arms for this signal have been ordered and the expected delivery date is September 25, 2020.

Three bids were received from; WL Contractors, Inc. Sturgeon Electric Company, Inc., and Berg Electric. W.L. Contractors, Inc. was the low bid at $470,207. Construction will begin once the contract has been executed. The contractor will have until December 30, 2020 to complete construction.

 

Project Bidding Process

A Request for Bids (RFB) was posted on the City’s website and the Rocky Mountain E-Purchasing System. Three valid bids were received on September 3, 2020. WL Contractors Inc. was the low bidder for the project.

 

Staff Responsible (Department Head):  Joe Wilson, Director of Public Works

Staff Member Presenting:  Brent Soderlin, City Engineer

 

Financial Impact$470,207

Funding SourceCapital Improvement and Preservation Plan Budget. E-470 Authority to refund City for 100% of cost up to $750,000 per IGA (attached).

 

Staff RecommendationApprove contract authorizing W.L. Contractors, Inc. to construct traffic signals at the interchange of 120th Avenue and E-470.

Suggested Motion:  I move to approve Resolution # 2020-69.