File #: Pres 19-152    Version: 1 Name:
Type: Presentation Status: Agenda Ready
File created: 3/7/2019 In control: City Council
On agenda: 4/22/2019 Final action:
Title: 2019 Core City Infrastructure Improvements and Irondale Neighborhood Plan “Quick Items”
Attachments: 1. Presentation, 2. Staff Memo
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

2019 Core City Infrastructure Improvements and Irondale Neighborhood Plan “Quick Items”

 

Body

Summary and Background InformationThe purpose of the 2019 Core City Infrastructure Improvements and Irondale Neighborhood Plan “Quick Items” is to plan/build infrastructure improvements within the Core City and Irondale to enhance the local neighborhoods.

-                     Core City improvements consist of

                     Mill & overlay of select local and collector streets

                     Upgrade signage, as appropriate

                     Building missing sections of sidewalk and ramps

-                     Irondale improvements include:

                     Mill and overlay of select local streets

                     Upgrade of signage, as appropriate

                     Local Drainage Implementation Plan

                     Identification/Purchase of properties & ROW to construct

-                     Retention/Detention Ponds

-                     Drainage Improvements/Storm Sewers

-                     Roadway Improvements

-                     Curb, gutter, sidewalks, streets, and street lighting

In addition to the mill & overlay projects recommended at the 8 April Study Session as part of the 2019 Pavement Management Program, Public Works is recommending the following:

-                     Core City: Installation of approximately 10,730 linear feet of sidewalk with associated curb, gutter and ramps at numerous locations south of E. 72th Avenue.

-                     Irondale: Drainage improvements as well as land acquisition research and ROW identification/purchase for the future installation of sidewalks, curb, gutter, ramps, and lighting.

  The specific approaches to accomplish this work include:

-                     Adding identified sidewalk work of existing flatwork contract.

-                     Coordinate drainage implementation plan through Urban Drainage Flood Control District.

-                     Hire Land Acquisition Company to research vacant properties for potential detention/retention pond sites and assist with right-of-way purchases.

-                     Hire Civil Engineer Design Firm(s) to assist with street/sidewalk design(s)

 

Staff Responsible (Department Head):  Joe Wilson, Director of Public Works

Staff Member Presenting:  Joe Wilson, Director of Public Works and Brent Soderlin, City Engineer

 

Financial Impact:  $2,120,000

Funding SourcePublic Works (Irondale Neighborhood Plan Fund - $620,000 and Core City Infrastructure Improvements Fund - $1,500,000)

 

Staff Recommendation: Public Works recommends Council approve suggested roadway, sidewalk, and drainage improvements recommended as part of the Core City Infrastructure Improvements and Irondale Neighborhood Plan “Quick Items” projects.