Title
RESOLUTION INCREASING CONSTRUCTION CONTRACT AUTHORIZATION FOR THE EAGLE POINTE RECREATION CENTER PROJECT
Body
Summary and Background Information: As part of the voter-approved capital bond program, Commerce City is renovating the Eagle Pointe Recreation Center located at 6060 Parkway Drive. Golden Triangle Construction was selected as the Construction Manager/General Contractor (CM/GC) and awarded a contract for preconstruction services including preparation and submittal of a Guaranteed Maximum Price (GMP) proposal for the construction work. The final GMP contract value was established at $13,010,922 with the approval of Resolution 2018-13
. The resolution also authorized the City to negotiate and execute changes up to 5% ($650,546) of the GMP contract for a total authorization of $13,661,468 without further Council approval. To date, the project has added the following additional scope items, which used a majority of the 5% contract contingency:
Replace Existing Pool Deck* $ 250,804
Additional parking lot concrete repairs $ 56,906
Bid Alternate #05: Replace 2nd floor track surface $ 51,491
Facility system upgrades for elevator modernization $ 48,129
Total Scope Enhancements $ 407,330
Other Construction Change Orders $ 214,072
AUTHORIZED CONTINGENCY USED TO DATE: $ 621,402
AUTHORIZED CONTINGENCY REMAINING: $ 29,144
*Funded through Adams County Open Space Grant
The remaining construction contingency budget is $520,347. The project team anticipates further changes will need to be negotiated to successfully complete the Eagle Pointe Recreation Center renovation. Increasing the authorization to negotiate change orders up to 7% of the GMP value will allow construction to continue without schedule impacts. The additional 2% authorization equals a dollar am...