Summary and Background Information: As part of the Measure 2K Bond Program, the City plans to build additions and renovations to the Eagle Pointe Recreation Center located at 6060 Parkway Drive. Golden Triangle Construction (GTC) was selected as the Construction Manager/General Contractor (CM/GC) and awarded a contract for preconstruction services including preparation and submittal of a Guaranteed Maximum Price (GMP) proposal for the construction work. The CM/GC's services during the Construction Services phase include, but are not limited to, construction management, administration, field supervision, coordinating subcontractors, maintaining quality, meeting schedules and providing the general conditions work for the Project. A benefit of CM/GC delivery is the ability to overlap design and construction through the use of construction packages. The New Recreation Center and Infrastructure will be delivered through two packages
Package 1 - Building Addition Foundations and Utility Relocations
Package 2 - Building Addition, Interior Renovations and Final Site Work
Design of Package 1 is complete and has been competitively bid amongst subcontractors by GTC. The GMP has been prepared based upon subcontractor pricing plus additional costs as detailed below:
General Conditions * $515,199
Construction Costs $183,797
Weather Protection Allowance $10,000
Utility Relocation Allowance $37,500
Permit Fees $8,207
Insurance $8,144
Payment & Performance Bonds $6,284
Contractor Contingency (4%) $30,765
Overhead and Profit (3.5%) $26,920
Total GTC GMP Package 1 $826,816
Owners Contingency (5%) $41,341
Total Council Approval $868,157
* General Conditions are for the entire project - both Package 1 and Package 2

Staff Responsible (Department Head): Director of External Affairs Halstead
Staff Member Presenting: 2K Program Director Hergenrader

Financial Impact: $868, 15...