File #: Res 2017-73    Version: 1 Name: Hwy 2 design contract amendment
Type: Resolution Status: Passed
File created: 7/19/2017 In control: City Council
On agenda: 8/7/2017 Final action: 8/7/2017
Title: RESOLUTION APPROVING AMENDMENT TO CONTRACT FOR HIGHWAY 2 WIDENING PROFESSIONAL SERVICES
Attachments: 1. Resolution, 2. HDR Amendment 4 Agreement, 3. Presentation

Title

RESOLUTION APPROVING AMENDMENT TO CONTRACT FOR HIGHWAY 2 WIDENING PROFESSIONAL SERVICES

 

Body

Summary and Background Information

Based on an unknown outcome and timeframe on being able to obtain BNSF ROW, Commerce City has made the decision to move forward, in parallel with still trying to obtain BNSF ROW, with preparing design alternatives to construct the roadway completely outside of BNSF ROW. Implementing this plan will mitigate a potential construction delay that could result in additional contractor general condition costs. This decision requires additional design and results in the need to amendment HDR’s contract to support this work. Also included in this amendment are costs for the re-design of the Derby area to increase parking as directed by City Council, costs associated with the prolonged condemnation process for both BNSF and V-Co, and additional allowance for design support during construction.

 

This contract amendment of $399,269 requires council approval.

 

Staff Responsible (Department Head):  Michelle Halstead

 

Staff Member Presenting:  Michelle Halstead

 

Financial Impact:           

Original Contract         $1,802,967                                          

Amendment #1                        $167,708

Amendment #2                                            $0  (Time Extension Only)

Amendment #3                         $50,000

Amendment #4                       $399,269

Total Contract                                $2,419,944

 

Funding Source:  General Fund

Staff RecommendationThe Project Management team recommends amending the HDR contact by $399,269 for a total contract value of $2,419,944.