RESOLUTION APPROVING AWARD OF CONTRACT FOR NEW RECREATION CENTER AND INFRASTRUCTURE CONSTRUCTION SERVICES (WORK PACKAGE A)

 

Body

Summary and Background InformationAs part of the Measure 2K Bond Program, the City plans to build a recreation facility located at approximately Highway 2 and 112th Ave. and associated infrastructure to include roadway improvements and utilities. Pinkard Construction was selected as the Construction Manager/General Contractor (CM/GC) and awarded a contract for preconstruction services including preparation and submittal of a Guaranteed Maximum Price (GMP) proposal for the construction work. The CM/GC's services during the Construction Services phase include, but are not limited to, construction management, administration, field supervision, coordinating subcontractors, maintaining quality, meeting schedules and providing the general conditions work for the Project.

 

A benefit of CM/GC delivery is the ability to overlap design and construction through the use of construction packages.  The New Recreation Center and Infrastructure will be delivered through four packages:

Package A - Infrastructure West

Package 1 - Building Site and Foundations

Package 2 - Building

Package B - Infrastructure East

 

Design of Package A - Infrastructure West is complete and has been competitively bid amongst four prequalified contractors.  Details of the process will be provided once negotiations are completed with the selected contractor. The GMP has been prepared based upon subcontractor pricing plus additional costs as detailed below:

Construction Costs

$11,317,014

Permits & Taxes

$513,034

General Conditions

$710,385

Contractor Contingency (2.25%)

$282,745

Overhead and Profit (3.95%)

$507,543

Insurance

$109,337

Payment & Performance Bonds

$93,583

Weather Protection Allowance

$100,000

Utility Sequence Allowance

$120,000

Total Pinkard GMP Package A

$13,753,641

Owners Contingency (5%)

$687,682

Total Council Approval

$14,441,323

 

Staff Responsible (Department Head):  Interim Director of External Affairs Halstead

Staff Member Presenting: Scott Hergenrader (CH2M Hill)

 

Financial Impact: $14,441,323

Funding Source:  2K

 

Staff RecommendationAward of Construction Services for Package A to Pinkard Construction Company

Suggested Motion:  I move to approve Resolution 2016-100.