File #: Res 2014-65    Version: 1 Name: Resolution 2014-65
Type: Resolution Status: Passed
File created: 5/21/2014 In control: City Council
On agenda: 6/2/2014 Final action: 6/2/2014
Title: RESOLUTION APPROVING AGREEMENT BETWEEN THE CITY OF COMMERCE CITY AND SUNCOR ENERGY (U.S.A.) PIPELINE COMPANY FOR RELOCATION OF A CRUDE OIL PIPELINE AND REIMBURSEMENT THEREFOR
Attachments: 1. Resolution, 2. Agreement, 3. Project Information
Title
RESOLUTION APPROVING AGREEMENT BETWEEN THE CITY OF COMMERCE CITY AND SUNCOR ENERGY (U.S.A.) PIPELINE COMPANY FOR RELOCATION OF A CRUDE OIL PIPELINE AND REIMBURSEMENT THEREFOR
 
Body
Summary and Background Information:  
The Suncor Energy Pipeline Company has an existing ten (10) inch diameter crude oil pipeline located within the 104th Avenue right-of-way. As a part of the 104th Avenue widening project, Suncor must make certain modifications to the pipeline. Suncor is sharing the costs of these modifications with the city, subject to the terms and conditions contained in the Pipeline Modification and Reimbursement Agreement. This agreement has been reviewed and approved by Suncor and has been reviewed and is recommended for approval by city staff along with the change order.
The total estimated cost of the pipeline replacement is $738,092, including $70,875 if rock is encountered during boring operations. Per the Agreement, the city would be responsible for 50% of these costs or $369,046.
 
Staff Responsible (Department Head):  Maria D'Andrea, Director of Public Works
Staff Member Presenting:  N/A
 
Financial Impact:  $369,046.00
Funding Source:  Commerce City Northern Infrastructure GID
 
Staff Recommendation:  Approve the resolution.
 
 
Suggested Motion:  I move to approve Resolution #2014-65.