File #: Res 2014-64    Version: 1 Name: Approving Change Order No. 3 for East 104th Avenue, Phase 3B Improvements Project
Type: Resolution Status: Passed
File created: 5/21/2014 In control: City Council
On agenda: 6/2/2014 Final action: 6/2/2014
Title: RESOLUTION APPROVING CHANGE ORDER NO. 3 TO AGREEMENT BETWEEN THE CITY OF COMMERCE CITY AND ZAK DIRT, INC. FOR EAST 104TH AVENUE IMPROVEMENTS PROJECT, PHASE 3B
Attachments: 1. Resolution, 2. Change Order No. 3 Information
Title
RESOLUTION APPROVING CHANGE ORDER NO. 3 TO AGREEMENT BETWEEN THE CITY OF COMMERCE CITY AND ZAK DIRT, INC. FOR EAST 104TH AVENUE IMPROVEMENTS PROJECT, PHASE 3B
 
Body
Summary and Background Information:  
 
The South Adams County Water and Sanitation District (SACWSD) owns an easement under 104th Avenue in the vicinity of the project area to transport water to the district's Tanabe surface water storage facility. This change order includes work to install a raw water pipeline in the 104th Avenue right-of-way to replace the easement. Staff has been working with SACWSD staff on the design of the pipeline for several months. Because the design was not yet complete at the time of project bidding, installation of the water line was not included in the base bid; however, funds were included in the project budget to cover these costs.
 
 
Staff Responsible (Department Head):  Maria D'Andrea, Director of Public Works
Staff Member Presenting:  N/A
 
Financial Impact:  $396,803.99
Funding Source:  Commerce City Northern Infrastructure GID
 
Staff Recommendation:  Approve the resolution.
 
Suggested Motion:  I move to approve Resolution #2014-64.