RESOLUTION APPROVING AWARD OF THIRD AMENDMENT TO CONTRACT FOR NEW RECREATION CENTER AND INFRASTRUCTURE CONSTRUCTION SERVICES (WORK PACKAGE 2)
Body
Summary and Background Information:
As part of the 2K Bond Measure Program, the city plans to build a recreation facility located at approximately Highway 2 and 112th Ave. and associated infrastructure to include roadway improvements and utilities. Pinkard Construction was selected as the Construction Manager/General Contractor (CM/GC) and awarded a contract for preconstruction services including preparation and submittal of a Guaranteed Maximum Price (GMP) proposal for the construction work.
The CM/GC's services during the construction services phase include, but are not limited to: construction management, administration, field supervision, coordinating subcontractors, maintaining quality, meeting schedules and providing the general conditions work for the project.
A benefit of CM/GC delivery is the ability to overlap design and construction through the use of construction packages. The new recreation center and infrastructure will be delivered through four packages:
Package A - Infrastructure West
Package 1 - Building Site and Foundations
Package 2 - Building
Package B - Infrastructure East
Award of construction services for Package A - Infrastructure West was approved on August 22, 2016, establishing the initial GMP. The first amendment to incorporate Package 1 - Building Site and Foundations was approved on October 3, 2016. A second amendment incorporating Change Order No. 2 reflecting an IGA with SACWSD to add an irrigation line was approved on November 7, 2016. This amendment seeks to increase the GMP by incorporating Package 2 - balance of the Building construction. See GMP breakout below.
Item Amount
Package 1 Construction Costs $19,808,841
General Conditions (included Pkg 1) $0
Moisture Mitigation Allowance $40,000
Interior Graphic/Signage Allowance $50,000
Exterior Graphic/Signage Allo...