File #: Ord 2421    Version: Name:
Type: Ordinance Status: Passed
File created: 8/5/2022 In control: City Council
On agenda: 10/17/2022 Final action: 10/17/2022
Title: SECOND AND FINAL READING OF AN ORDINANCE AMENDING THE 2022 BUDGET OF THE CITY OF COMMERCE CITY, COLORADO BY THE RECOGNITION OF THE COLORADO DEPARTMENT OF TRANSPORTATION GRANT IN THE AMOUNT OF $3,000,000 FOR 88TH AVE:I-76 TO HIGHWAY 2 AND THE AUTHORIZATION OF THE EXPENDITURE THEREOF.
Attachments: 1. Council Communication, 2. Ordinance 2421
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
10/17/20222 City Council approved on second & final reading  Action details Meeting details Not available
9/19/20222 City Council introduced by council as seated and approved on first readingPass Action details Meeting details Not available

Title

SECOND AND FINAL READING OF AN ORDINANCE AMENDING THE 2022 BUDGET OF THE CITY OF COMMERCE CITY, COLORADO BY THE RECOGNITION OF THE COLORADO DEPARTMENT OF TRANSPORTATION GRANT IN THE AMOUNT OF $3,000,000 FOR 88TH AVE:I-76 TO HIGHWAY 2 AND THE AUTHORIZATION OF THE EXPENDITURE THEREOF.

 

Body

Summary & Background

At the 15 March City Council meeting, an Intergovernmental Agreement (IGA) between the City and the Colorado Department of Transportation (CDOT) was approved to advance the design of 88th Avenue. The IGA is for the administration of the DRCOG grant that we received in 2020. The DRCOG grant is broken out as a 75/25 split between DRCOG/CDOT and the City ($3,000,000 from DRCOG and $1,000,000 from Commerce City).

 

The project will improve approximately 1.6 miles of E. 88th Avenue between Interstate 76 (I-76) and Highway 2. The purpose of the 88th Avenue Widening Project is to improve traffic operations and accommodate current and future general vehicular traffic, heavy trucks, bicycles, and pedestrians on East 88th Avenue between I-76 and Highway 2. The East 88th Avenue corridor has one travel lane in each direction with signalized intersections at the northbound I-76 on/off ramps, Brighton Road, Rosemary Street, and Highway 2.

 

The original IGA with CDOT for the DRCOG grant does not spell out the right-of-way acquisition, also broken out as a 50/50 split between DRCOG/CDOT and the City.  Through amendment, spell out the right-of-way and split into 75/25. 

 

Staff Responsible (Department Head): Joe Wilson, Director of Public Works

Staff Presenting: Joe Wilson, Director of Public Works

 

Funding Source: $3,000,000 grant from DRCOG/CDOT and $1,000,000 from the 88th Widening project fund

 

Staff Recommendation: Approval of Ordinance 2421

Suggested Motion: Motion to approve Ordinance 2421