Buffalo Run Clubhouse Update

 

Body

Summary & Background

The Parks, Recreation and Golf department is giving an updated presentation of the Buffalo Run Clubhouse renovation/expansion.   

 

Prior meeting dates to the clubhouse project are:

8/19/24 (Executive Session)

7/22/24

4/8/24

9/14/23 (Meeting at Bison Grill, not an official study session)

4/25/22

 

The budget of the clubhouse is $13,677,240.  The 7/22/24 meeting confirmed that updated bids requested by council were still over budget.  Council discussed wanting to see the project within budget.  Also discussed by council was several options:

*Minimum budget to "refresh" the clubhouse

*What can be completed without using entire budget

*What can be completed using entire budget

*Vacating project

 

These 4 options will be presented with estimated totals of construction for each option. 

 

Staff will be asking council for a final recommendation of the 4 options.

 

Staff Responsible (Department Head): Chad Redin, Director, Parks, Recreation and Golf

Staff Presenting: Chad Redin, Director, Parks, Recreation and Golf