File #: Res 2016-119    Version: 1 Name: Second Amendment to Pinkard GMP Contract for New Recreation Center Construction Package 2
Type: Resolution Status: Passed
File created: 10/3/2016 In control: City Council
On agenda: 12/19/2016 Final action: 12/19/2016
Title: RESOLUTION APPROVING AWARD OF THIRD AMENDMENT TO CONTRACT FOR NEW RECREATION CENTER AND INFRASTRUCTURE CONSTRUCTION SERVICES (WORK PACKAGE 2)
Attachments: 1. Resolution, 2. Presentation

Title

RESOLUTION APPROVING AWARD OF THIRD AMENDMENT TO CONTRACT FOR NEW RECREATION CENTER AND INFRASTRUCTURE CONSTRUCTION SERVICES (WORK PACKAGE 2)

 

Body

Summary and Background Information

As part of the 2K Bond Measure Program, the city plans to build a recreation facility located at approximately Highway 2 and 112th Ave. and associated infrastructure to include roadway improvements and utilities. Pinkard Construction was selected as the Construction Manager/General Contractor (CM/GC) and awarded a contract for preconstruction services including preparation and submittal of a Guaranteed Maximum Price (GMP) proposal for the construction work.

The CM/GC's services during the construction services phase include, but are not limited to: construction management, administration, field supervision, coordinating subcontractors, maintaining quality, meeting schedules and providing the general conditions work for the project.

A benefit of CM/GC delivery is the ability to overlap design and construction through the use of construction packages.  The new recreation center and infrastructure will be delivered through four packages:

Package A - Infrastructure West

Package 1 - Building Site and Foundations

Package 2 - Building

Package B - Infrastructure East

 

Award of construction services for Package A - Infrastructure West was approved on August 22, 2016, establishing the initial GMP.  The first amendment to incorporate Package 1 - Building Site and Foundations was approved on October 3, 2016.  A second amendment incorporating Change Order No. 2 reflecting an IGA with SACWSD to add an irrigation line was approved on November 7, 2016.  This amendment seeks to increase the GMP by incorporating Package 2 - balance of the Building construction.  See GMP breakout below.

 

Item

Amount

Package 1 Construction Costs

$19,808,841

General Conditions (included Pkg 1)

$0

Moisture Mitigation Allowance

$40,000

Interior Graphic/Signage Allowance

$50,000

Exterior Graphic/Signage Allowance

$50,000

Pool Theming and Graphics Allowance

$100,000

Art Wall Screen Allowance

$50,000

Contractor Contingency

$452,224

Insurance and Bonds:

$286,858

Contractor's CM/GC Fee (3.95% - excludes bonds & insurance)

$811,767

Guaranteed Maximum Price - Package 1

$21,649,690

Package A GMP

$13,563,509

Package 1 GMP

$12,144,680

Change Order No. 2

$908,277

Total Guaranteed Maximum Price:

$48,266,156

Owners Contingency (5%)

$2,462,656

Permits and Taxes (direct paid by City)

$986,967

Total Council Authorization

$51,715,779

 

Staff Responsible (Department Head):  Interim Director of Intergovernmental Services Michelle Halstead

Staff Member Presenting:  Scott Hergenrader (CH2M)

 

Financial Impact:  $51,715,779

Funding Source: 2K

 

Staff Recommendation: Amend the Pinkard Construction Services Contract to incorporate Building Package 2 into the total Guaranteed Maximum Price 

Suggested Motion:  I move to approve Resolution 2016-119